Road Cutting Permissions
|
G.O.Ms.No.50, TS-iPASS(Telangana State Industrial Project Approval and Self Certification System)Rules.
Click Here
|
Timeline:
- Online Application Submission by the Applicant.
- Application Scrutiny, Physical Verification by the Executive Eng ineer, R & B and Final Approval within 6 days after receiving the Application.
- Payment of Fees by Applicant after Clearance
- Final Permission Letter Issued - Within 1 day after payment of Fees
Final permission Letter will be issued within 7 days of the Application provided all application documents are in order and no delay in fee payment.
|
Documents:
The applicant should submit the application form along with all the necessary documents stated in the below and pay the fees online itself for getting the approval.
- Covering Letter Requesting the Road Cutting/ Right of Way Permission.
- Route/Road map with Clear Road Dimension Details, Planned Activities, Location/Address.
|
Procedure:
|
G.O.Ms.No.52, Process Document for Road Cutting Permission/Right of Way Permission: Click Here |
User Guide:
- Road Cutting/ Right of Way Permissions Portal - Entrepreneur: Click Here
- Road Cutting/ Right of Way Permissions Portal - DISCOMS: Click Here
- Road Cutting/ Right of Way Permissions Portal - Approval Authority: Click Here
|
Apply here:
|
Online Road Cutting Permission/ Right of Way permission: Click Here |
Dashboard:
|
Road Cutting Permission Dashboard: Click Here |